Adjacent to Baiyangdian Lake, providing farm drainage and flood relief; 8.7 km treated with a complete water-circulation system.
Key parameters and scope of the project
| 项目要素 / Key Fact | 内容 / Detail |
|---|---|
| Project Type | Water & Environment · Alkali-drainage Ditch Comprehensive Treatment (incl. O&M) |
| Contract Value | ¥34.81 million |
| Project Name | Anxin County Dazhangzhuang Alkali-drainage Ditch Comprehensive Treatment Project |
| Location | East of Anxin County town, Xiong'an New Area, Hebei, outside the Baiyangdian embankment (bordering Daqugou to the north) |
| Treatment Length | 8.7 km (channel 9.8 km in total: 7.6 km main ditch + 2.2 km branch) |
| Layout | "D"-shaped, covering an area of 5.84 km² |
| Villages Involved | Dazhangzhuang, Xiaozhangzhuang, Xiaotianzhuang, Songzhuang, Dongliujie, Beilianjie |
| Main Function | Alkali drainage and flood relief for the surrounding farmland |
| Main Works | Removal of domestic waste along both banks and in the channel, demolition of dry toilets, dredging and disposal of bottom sludge, treatment of existing in-channel wastewater, desilting and clearance excavation, bank restoration and earth filling |
| Pumping Station | 1 station, capacity 1.4 m³/s |
| Gates | 1 control gate and 1 stop-log gate |
| Aeration | 10 flow-pushing aerators |
| O&M Services | Operation, maintenance and related services included |
| Construction Period | 210 days |
| Acceptance | Completion acceptance passed (on-site inspection plus final acceptance review meeting) |
Overview · Main works · Pumping station, gates and aeration · Construction period
The Anxin County Dazhangzhuang alkali-drainage ditch comprehensive treatment project lies just east of Anxin County town, outside the Baiyangdian embankment, bordering Daqugou to the north. It mainly serves alkali drainage and flood relief for the surrounding farmland.
The ditch is 9.8 km long in total — 7.6 km of main ditch and 2.2 km of branch — passing through Dazhangzhuang, Xiaozhangzhuang, Xiaotianzhuang, Songzhuang, Dongliujie and Beilianjie villages. This treatment covers 8.7 km in a "D"-shaped layout over an area of 5.84 km².
Removal of domestic waste along both banks and in the channel; demolition of dry toilets along the ditch; dredging and disposal of bottom sludge; treatment of existing in-channel wastewater; desilting and clearance excavation; bank restoration and earth filling. The works also include 1 pumping station (capacity 1.4 m³/s), 1 control gate and 1 stop-log gate, 10 flow-pushing aerators, plus operation and maintenance services.
Combining external-source control with internal-source treatment, the bottom sludge was dredged and the banks restored to eliminate internal pollution. The new pumping station, control gate and stop-log gate together with 10 flow-pushing aerators form a complete water-circulation and aeration system. Water quality passed sampling tests, and before-and-after comparisons show marked improvement — clear water and green banks, with the alkali-drainage, flood-relief and ecological functions restored.
The construction period was 210 days. The project has passed completion acceptance, comprising on-site inspection and a final acceptance review meeting.
Treatment results, water quality sampling, before-and-after comparisons and completion acceptance